Prototype update: Initial Cultures for Test Cell
Over the past 30 days, significant progress has been made on the construction of the first test cell and the auxiliary systems and facilities. The greenhouse and lab are up and being outfitted and will be growing our initial cultures of algae starting August 6th. Construction of the canopy for the first test cell is underway and the cell will be capped and pressurized in the coming weeks. Simultaneously, the nutrient and CO2 delivery systems will be installed. The completion of these projects will enable the first cell to be inoculated in early September. Concurrently, construction of the second, third, and fourth test cells is scheduled to begin on August 11th.